Westinghouse Awarded Front-End Engineering and Design Study in Slovakia

Study will Advance AP1000® Engineering, Licensing and Project Planning for Jaslovské Bohunice Site

CRANBERRY TOWNSHIP, Pa.--(BUSINESS WIRE)--Westinghouse Electric Company has launched a Front-End Engineering and Design (FEED) study, funded in part by a grant from the U.S. Department of State’s Foundational Infrastructure for Responsible Use of Small Modular Reactor Technology (FIRST) Program, for one advanced AP1000® modular reactor at Jaslovské Bohunice Nuclear Power Plant in Slovakia. The work is being conducted for Jadrová energetická spoločnosť Slovenska (JESS), a wholly owned subsidiary of state-owned Jadrová a vyraďovacia spoločnosť (JAVYS), which is responsible for developing Slovakia’s new nuclear plant.

This comprehensive six-month study will advance engineering, licensing and project planning activities for the Jaslovské Bohunice project. The FEED study represents a significant step forward in the country's ambitious strategy to reduce its reliance on foreign energy sources to gain energy independence.

“The start of work on the FEED study marks a significant milestone for JESS and brings the preparation of the new nuclear power plant in Jaslovské Bohunice one step closer to implementation,” said Tomáš Vavruška, CEO of JESS. “Thanks to cooperation between the Slovak Republic and the United States under the intergovernmental agreement, we can assess the suitability of deploying AP1000 technology at this site and obtain more detailed technical and project documentation, including a preliminary schedule and budget. The results of the study will provide JESS with an important basis for deciding on the next steps in the project.”

“We thank the Slovak and U.S. governments for their close cooperation on civil nuclear power and for U.S. support in leading the FEED financing,” said Petr Brzezina, President of Westinghouse Czech and Slovakia. “Not only would an AP1000 plant at Jaslovské Bohunice deliver real economic benefits and high-quality jobs to Slovakia for generations, it can also foster the country’s energy independence.”

The advanced AP1000 reactor is the only operating Generation III+ reactor with fully passive safety systems, modular construction design and the smallest footprint per MWe on the market among large-scale reactors. There are six AP1000 reactors currently setting operational performance and availability records worldwide with 14 additional reactors under construction and a few in contractual phases. The AP1000 technology has been selected for nuclear energy programs in Poland, Bulgaria and Ukraine and is also under consideration at multiple other sites in Europe, the Middle East and North America.

About Westinghouse

Westinghouse delivers nuclear energy the world needs to meet rising electricity demand, support growing economies, strengthen energy security and power millions of homes across five continents. The company designs and deploys advanced nuclear reactors, manufactures the fuel that powers them, maintains and modernizes operating plants and advances tomorrow’s breakthroughs. Founded in 1886, the company electrified the industrial economy and pioneered nuclear power with the first commercial pressurized water reactor in 1957. Today, Westinghouse technology powers 57% of the world's nuclear power plants, maintains nearly two-thirds of the world's nuclear fleet and fuels 40% of that fleet. As the global leader in deployment of nuclear power at scale, Westinghouse has one of the largest new build pipelines in the industry.

From nuclear’s first chapter to its next, Westinghouse turns possibility into power.

Contacts

Industry:

Westinghouse Electric Company


Release Versions

Contacts

More News From Westinghouse Electric Company

Westinghouse Canada Awards BWXT AP1000® Manufacturing Qualification Contracts

CAMBRIDGE, Ontario--(BUSINESS WIRE)--Westinghouse Electric Company and BWXT Canada (NYSE: BWXT) have agreed to qualify BWXT Canada to manufacture key AP1000® components to Westinghouse specifications, supported by access to Westinghouse designs, manufacturing expertise, facilities and lessons learned. The qualification is being facilitated by Westinghouse purchase orders to fabricate demonstration pieces for steam generators in BWXT’s Cambridge, Ontario, facility in Canada and reactor vessel in...

Westinghouse Names Dayan Abeyaratne Chief Commercial Officer

CRANBERRY TOWNSHIP, Pa.--(BUSINESS WIRE)--Westinghouse Electric Company today announced the appointment of Dayan Abeyaratne as Chief Commercial Officer. In this role, Mr. Abeyaratne will lead the company’s global new plant dealmaking and strategic external affairs as Westinghouse advances the deployment of fleet-scale nuclear power worldwide. “Dayan brings significant industry and transaction experience that will support Westinghouse’s commercial and strategic objectives,” said Dan Sumner, West...

Westinghouse Awarded ARPA-E Funding to Accelerate PowerBlock™ Nuclear Fuel Technology

CRANBERRY TOWNSHIP, Pa.--(BUSINESS WIRE)--Westinghouse Electric Company announced today that it has been selected by the U.S. Department of Energy’s Advanced Research Projects Agency-Energy (ARPA-E) for funding through the High-performance Optimized Recycled Nuclear Isotopes for Gen IV reactors (HORNIG) program to support the continued development of PowerBlock™, an advanced nuclear fuel technology. The project will draw on Westinghouse’s nuclear fuel and manufacturing expertise to further adva...
Back to Newsroom